Project

Monopole Footer for National Grid

Location

Syracuse, NY

Owner

National Grid

Duration

3 Weeks

Project Overview

Westside Construction Group recently completed a critical monopole footer project for National Grid in Syracuse, NY. This project required precise excavation, meticulous rebar embedding, and concrete pouring to ensure a stable and durable foundation for the monopole.

Project Details

Location: Syracuse, NY
Scope of Work: Monopole Footer Construction

Project Objectives

The primary objectives of this project were to:

  • Excavate to Depth: Carefully excavate the site to the required depth for the monopole footer.
  • Complete Bottom Pad with Embedded Rebar and Threaded Rod: Install rebar and threaded rod into the bottom pad, ensuring structural integrity and stability.
  • Protect Threaded Rod: Implement measures to protect the threaded rod during the construction process.
  • Pour Remaining Concrete with Vertical Forms: Use vertical forms to pour the remaining concrete to a fixed elevation, achieving the specified design requirements.

Challenges and Solutions

Precise Excavation

  • Challenge: Achieving the required depth and dimensions for the monopole footer necessitated precise excavation.
  • Solution: Our skilled excavation team utilized advanced equipment to ensure accurate depth and dimensions, laying the groundwork for a stable foundation.

Rebar Embedding and Threaded Rod Installation

  • Challenge: Embedding rebar and threaded rods accurately was crucial for the footer’s structural integrity.
  • Solution: Our team meticulously installed the rebar and threaded rods in the bottom pad, adhering to engineering specifications to ensure maximum strength and stability.

Protecting Threaded Rod

  • Challenge: Protecting the threaded rod during the construction process was essential to maintain its integrity.
  • Solution: We implemented protective measures, including specialized coverings and careful handling procedures, to safeguard the threaded rods throughout the construction.

Pouring Concrete with Vertical Forms

  • Challenge: Pouring the remaining concrete with vertical forms required precision to reach the fixed elevation.
  • Solution: Our concrete team used high-quality vertical forms and precise pouring techniques to ensure the concrete reached the fixed elevation, resulting in a robust and level monopole footer.

Results

  • Accurate Excavation: Successfully excavated to the required depth, providing a solid foundation for the monopole footer.
  • Sturdy Rebar and Rod Installation: Installed rebar and threaded rods with precision, ensuring the footer’s structural integrity.
  • Protected Components: Effectively protected the threaded rods, maintaining their integrity during construction.
  • Precise Concrete Pouring: Achieved the fixed elevation with vertical forms, resulting in a stable and durable monopole footer.

Why Choose Westside Construction Group for Your Projects?

  • Expertise in Complex Projects: Our team has extensive experience in handling complex construction projects, ensuring precision and reliability.
  • Commitment to Quality: We uphold the highest standards of workmanship, ensuring every project meets engineering specifications and client expectations.
  • Advanced Techniques and Equipment: We use state-of-the-art equipment and innovative techniques to deliver superior results.
  • Safety and Integrity: Safety is our top priority, and we adhere to strict protocols to protect our team and the structural components during construction.